Weekly Roadwork - Schuylkill County

Published On: Aug 10 2011 10:18:30 PM EDT
generic_traffic_app_header

Information provided by PennDOT


WEEK of 8/22/16


City of Pottsville & Palo Alto Borough
ROAD NAME: PA 61
BETWEEN: Bacon Street AND US 209/Mauch Chunk Street
Type of Work: Bridge Repair
RESTRICTION: There will be a single lane on PA 61 northbound and southbound. This
The project began in Jan. 2014 and is expected to be complete this fall.
START DATE: 08/23/2016
Est. Completion Date: 08/24/2016
Restrictions in Effect (time of day): 9:00 AM To 5:00 PM
Will Rain Cause Delays? YES


Municipality: North Manheim & South Manheim Twps.
ROAD NAME: Berne Drive
BETWEEN: PA 443 AND PA 895
Type of Work: Drainage
RESTRICTION: Lane restriction with flagging for drainage work.
START DATE: 08/22/2016  
Est. Completion Date: 08/26/2016
Restrictions in Effect (time of day): 7:00 AM To 3:00 PM
Will Rain Cause Delays?



Municipality: Butler Twp
ROAD NAME: High Road
BETWEEN: PA 901 AND Northumberland County Line
Type of Work: Other
RESTRICTION: Lane restriction with flagging base repair.
START DATE: 08/22/2016  
Est. Completion Date: 08/26/2016
Restrictions in Effect (time of day): 7:00 AM To 3:00 PM
Will Rain Cause Delays? YES



Municipality: E. Brunswick & N. Manheim Twps.
ROAD NAME: PA 61
BETWEEN: Port Clinton Borough AND City of Pottsville
Type of Work: Brush Cutting
RESTRICTION: No Restrictions for brush cutting work. Please use caution.
START DATE: 08/22/2016  
Est. Completion Date: 08/26/2016
Restrictions in Effect (time of day): 7:00 AM To 3:00 PM
Will Rain Cause Delays?



Municipality: Wayne Township
ROAD NAME: PA 895
BETWEEN: PA 61 AND PA 183
Type of Work: Bridge Repair
RESTRICTION: PA 895 will be closed and detoured for repairs to the bridge over Bear Creek. Crews will be performing a steel beam superstructure replacement. Traffic will be detoured on PA 61, PA 443 and PA 183. Local access will be maintained on either side of the bridge.
START DATE: 08/08/2016  
Est. Completion Date: 08/26/2016
Restrictions in Effect:  24 Hours
Will Rain Cause Delays? YES



ROAD NAME: Forrest Lane
BETWEEN: US 209 AND PA 901
Type of Work: Milling & Paving
RESTRICTION: Lane restriction with flagging for milling and paving work
START DATE: 07/29/2018  
Est. Completion Date: 08/30/2016
Restrictions in Effect (time of day): 7:00 AM To 7:00 PM
 

Municipality: Pine Grove and Tremont Townships
ROAD NAME: Interstate 81
BETWEEN: Exit 100 (Pine Grove) AND Exit 104 (Ravine)
Type of Work: Construction
RESTRICTION: Interstate 81 will be reduced to single lane conditions with traffic in both directions being shifted to the northbound side for construction work related to the ongoing Interstate 81 Reconstruction Project.
START DATE: 05/18/2016  
Est. Completion Date: 12/01/2016
Type of Restriction: 24hours


Municipality: Bangor Borough
ROAD NAME: Messinger Street
BETWEEN: Messinger Street Bridge
Type of Work: Bridge Replacement
RESTRICTION:  Messinger Street will be closed and detoured between PA 191 and South Main Street. The posted detour will utilize PA 191, Flicksville Road, and South Main Street, or PA 191, PA 512, and North Main Street.  Updates on the project will be provided when available.
START DATE: 08/08/2016  
Est. Completion Date: 12/2017  
Restrictions in Effect (time of day): 24 Hours
Will Rain Cause Delays? YES